A major upgrade of the notorious Lindum open level crossing is moving ahead, with early works starting from 15 June despite ongoing delays from the Albanese Government.
Early works are progressing, despite the Albanese Government failing to sign off on the final $65 million in funding needed for this critical safety upgrade.
Energex will relocate underground electrical cables near Lindum Station and along Lindum Road from June 15.
These works are expected to take around four months, weather permitting, as the site is prepared for major construction in 2027.
The upgrade has been shaped by extensive community consultation undertaken in late 2024, with local feedback informing the final design as well as additional safety improvements.
Two fatalities have happened at the level crossing in the past eight years, making this project a priority.
The project will improve safety and connectivity for residents, commuters, pedestrians and cyclists by:
• realigning the crossing,
• reducing vehicle speeds to 40km per hour on all road approaches
• and installing new traffic signals, pedestrian crossings and shared pathways.
These improvements build on the recently completed Lindum Station accessibility upgrade and the first stage of safety works already delivered at the crossing, including median islands, an extended boom gate and an improved road surface.
Brisbane is one of Australia’s fastest-growing cities, yet critical infrastructure funding continues to lag behind population growth.
While rail infrastructure is typically funded by State and Federal governments, Council has committed $40 million towards open level crossings across Brisbane.
Residents have been kept informed throughout planning, with strong community support shown for the next stage and its focus on improving safety.
While the previous Federal Government signed off on jointly funding the project with Brisbane City Council and the Queensland Government, the Albanese Government has so far refused to contribute the final $65 million in funding.
Quotes attributable to Lord Mayor Adrian Schrinner:
“Rail crossings are generally the responsibility of State and Federal governments, but we’ve committed $40 million towards open level crossing projects across Brisbane.
“It’s disappointing the Federal Government continues to delay the final funding package for this important safety project while Brisbane’s population continues to grow.
“The Federal Government collects 81 cents in every tax dollar Australians pay, yet Brisbane continues to miss out on infrastructure funding.
“We’re committed to delivering this project and working with all levels of Government to keep Brisbane moving.”
Quotes attributable to Infrastructure Chair Cr Ryan Murphy:
“More than 1,000 days after the Albanese Government’s 100 day infrastructure review, the Lindum crossing upgrade still isn’t fully funded.
“Instead of trying to claim her predecessor’s work, Kara Cook should be telling her Federal Colleagues to sign off on the final $65m shortfall for this crucial project.
“The Schrinner Council is progressing this project in partnership with the Queensland Government, who have put funding on the table.
“Local governments collect three cents in every tax dollar but deliver a third of the services communities rely on.
“The Federal Government has been great at hitting Australians with new taxes but left wanting when it comes to ensuring the money is invested where it matters.”
Quotes attributable to Councillor Alex Givney:
“Lindum Station is a busy part of our community, so I’m thrilled to see this next stage moving ahead.
“Local residents expect their Federal representatives to fight for projects like this and secure Brisbane’s fair share of infrastructure funding.
“Residents have shared that safety at the level crossing was their top priority and this design responds directly to that feedback.”
Quotes attributable to Councillor Lisa Atwood:
“We know how important this crossing upgrade is for bayside residents, so we’ll continue working with other levels of government to deliver long-term safety improvements.”