Residents looking to cross the Brisbane River will still be able to use public transport during the three-week closure of the Story Bridge over the Christmas holidays.
The southern and northern approaches of the bridge will be resurfaced as part of the Schrinner Council’s Operation Smooth, which will see a record $110 million invested in road resurfacing.
The bridge will close to general traffic from 1am Sunday, 27 December until 5am Monday, 18 January.
All bus services that cross the Story Bridge will be diverted on temporary routes, with some passengers needing to change buses to complete their journey.
Five bus stops will need to close for the duration of the resurfacing, with alternate stops available nearby.
The Schrinner Council is working closely with Translink to minimise disruption for passengers while crews give the 86-year-old bridge a fresh resurfacing.
Temporary bus route changes include:
- Routes 227, 228, 231, 232 and 236: Services will divert via Wellington Road and Latrobe Street, with temporary stops 350 to 400 metres from affected Shafston Avenue stops.
- Routes 227, 232 and 234: The Main Street stop at Story Bridge East will close, with an alternative stop at Thornton Street, approximately 200 metres away.
- Routes 216, 221, 227, 228, 231, 232 and 236: Services will divert around Shafston Avenue at Connor Street, with alternative stops 250 to 500 metres away.
- Route N154: Five Main Street stops will no longer be serviced by this route. Passengers can use Route N226 to Wellington Street, with safe drop-offs available along the route.
Temporary bus stop closures include:
- Shafston Avenue at Salstone Street, stop 11. Residents can use the nearby stops on Latrobe Street and Wellington Road.
- Shafston Avenue at Connor Street, stop 10/6. Residents can use the nearby stops Main Street at St Vincents Hospital, Pearson Street, or River Terrace.
- Shafston Avenue at Connor Street, stop 7/10. Residents can use the nearby stops Main Street at St Vincents Hospital, Pearson Street, or River Terrace.
- Main Street at Story Bridge East, stop 6. Residents can use the nearby stop, Main Street at Thornton Street.
The closure has been deliberately scheduled during the quieter Christmas school holidays to reduce impacts on passengers and motorists.
Crews will work around the clock to resurface the bridge’s southern approach, complete structural maintenance and waterproof the road deck to help extend its life.
It’s just one of the many major roads being resurfaced as part of Operation Smooth, which will see almost one million square metres of Brisbane roads renewed this financial year.
From 30 November, Translink’s Journey Planner will show routes four weeks ahead, giving commuters a number of weeks to determine if their route will be impacted and to plan ahead.
Bus diversions will remain in place until 18 January, even if the resurfacing finishes ahead of schedule.
Quotes attributable to Transport Chair Cr Andrew Wines:
“The Story Bridge is a Queensland icon and we’re getting on with this important work over the quieter post-Christmas period to reduce disruption.
“Thousands of people rely on our buses every day and we’ve made sure they can still get where they need to go, with alternative stops just a short walk from the ones that are temporarily closed.
“We’ll have alternative public transport options in place to keep passengers moving while the Story Bridge gets the sequel it deserves.
“We’re working with the State Government to make sure Brisbane residents have plenty of time to plan ahead, with Translink’s Journey Planner expected to be updated well in advance.”